Implementer
Maynilad Water Services Inc.
Location
-unknown-
SDG
6
Brief Description
Will draw water from the Tullahan River and provide an additional supply of 1 MLD. Its water supply will reach 3,200 customers in Valenzuela City Status: Substantially Completed MBBR started operation last Oct 14, 2022 Product Water Sampling Conducted last Nov 16 for the determination of possible presence of radioactive substances from Tullahan River (PASSED) Waterlab Internal Testing Nov 30 (see next slide for result) Joint site inspection with DOH and LGU conducted Dec 12 for the Drinking Water Site Clearance. Third party water sampling by Mac Union conducted Dec 12 Replacement of filter Media for Pre-filter ongoing (from silica sand to AFM glass media