Implementer
Maynilad Water Services Inc.
Location
-unknown-
SDG
6
Brief Description
-Silt Curtain Installation 100% completed last July 2, 2022 - Dredging works Total dredged volume target: 44,000 (cu.m. wet) Actual dredged volume to cater coverage area: 50,116.46 or 114% of the target. Dredging completed Nov. 30, 2022 - Hauling and Drying Total volume hauled: 2,203 out of 20,000 cu.m.